By Isla Quinn
Still water. A boat to cross it. A power station on the far side that no road reaches. Lake Manapōuri sits in the southwest of the South Island, at the edge of Fiordland National Park, and the township on its eastern shore is the westernmost municipality in New Zealand, according to Wikipedia. It is about a 20-minute drive from Te Anau. Wikipedia also says the town is the gateway to Doubtful Sound and Dusky Sound.
That is the postcard. Underneath it is a story about a power station, and about what a lake is worth.
The power station you cannot drive to
Engineering New Zealand’s heritage record describes an underground power station on the west arm of the lake, completed in 1971, with an installed capacity of 850 MW, making it New Zealand’s largest hydro-electric power station. Wikipedia adds that it has no road access, and that workers are ferried by boat.
The record gives a timeline. In July 1956 the Electricity Department announced a possible hydro project at the lake. On 19 January 1960 a company and the Government signed an agreement. In 1963 Consolidated Zinc decided it could not afford the station and the Government took over. Construction began in 1964. The machine hall was excavated from 1966 to 1968. In September 1969 the station generated power for the first time, and in 1972 it was fully commissioned.
The numbers are large. The record says the machine hall lies 200 metres below lake level, measures 111 metres long, 18 metres wide and 39 metres high, and that excavating it removed 1.4 million tonnes of rock. A spiralling vehicle tunnel about 2 kilometres long and a lift descending 193 metres give access. The station uses a 178-metre drop between the lake and Deep Cove in Doubtful Sound, through a tailrace tunnel 10 kilometres long. A second tailrace tunnel, also 10 kilometres long and 10 metres in diameter, was built between 1997 and 2002.
The record also says the project took almost eight million work hours and that 18 workers died. We include that because a place like this should not be described without it.
The petition
The power was meant for an aluminium smelter at Tiwai Point, at the entrance to Bluff Harbour, more than 150 kilometres from the station according to the heritage record. The campaign was about the lake.
The Otago Daily Times, in a 2020 article marking fifty years since the campaign, says the proposal would have raised Lake Manapōuri to the level of Lake Te Anau, about 27 metres. A study of the lakeshore vegetation, commissioned in October 1969, found, according to the article, that 26 vegetated islands were at risk and 19 would have been submerged. The article says raising the level would have produced only 4.6 per cent more electricity a year.
Opposition grew into the Save Manapouri Campaign. The newspaper says that by 1970 a petition had about 260,000 signatures, roughly a tenth of the country’s population at the time. Engineering New Zealand gives the figure 264,907. Both agree on the year and the scale.
What happened next
The newspaper says the campaign was a major issue in the 1972 election, which Labour won, and that in 1973 Prime Minister Norman Kirk pledged not to raise the lake levels. Engineering New Zealand puts the Government’s decision against raising lake levels in 1972. The two sources differ by a year on the decision, and we give both. The article adds that an independent body, the Guardians of Lakes Manapōuri, Monowai and Te Anau, was created to manage the lakes.
There is one wording we cannot reconcile. Engineering New Zealand also says that Stage Two added three more generators and “raised the lake level by 8 m”. The same record says the Government decided against raising levels. The record does not explain the apparent contradiction, so we do not either.
Wikipedia describes the campaign as the first mass environmental movement in New Zealand’s history, and a monument at the junction of State Highway 95 and Hillside Road marks it. That is Wikipedia’s wording, and we label it.
Going
Boats leave from Pearl Harbour, according to Wikipedia. Some cross the lake to the power station, and others go on by bus over Wilmot Pass to Doubtful Sound. We give no schedules or fares, which change.
What we left out
Capital cost, population figures, individual campaigners still living, and the names of tour operators. We have no sourced maker in Manapōuri to point to.
Roam first. Shop later.